Courtyard Paver Maintenance Project

Posted By on May 5, 2017

Courtyard paver maintenance for the following courtyards was approved: Bradford, Berkshire, Bainbridge, Devon, Elswick, Hampshire, Nelson, Durham Cheshire, Hallington and Lancaster.  During the paver maintenance, residents will not have access to their garages and will be required to park on the street.  The patrol company will not be citing vehicles during the paver project.  Below is the schedule for each courtyard.

 

Courtyards Start Date End Date
Bradford, Berkshire and Bainbridge June 6th at 8:00 a.m. June 9th at 10:00 a.m.
Devon, Elswick, Hampshire and Nelson June 20th at 8:00 a.m. June 23rd at 10:00 a.m.
Durham, Cheshire, Hallington and Lancaste June 27th at 8:00 a.m. June 30th at 10:00 a.m.

 

Any vehicles that drive on the courtyards while they are closed, will called to a hearing for any damages they cause to the pavers.